Maricopa County
Downtown Court Tower

Have a Question?

Project Schedule

October 2007 to September 2008
Schematic Design

September 2008 to March 2009
Design Development

March 2009 to October 2009
Final Plans-(Core shell Jul. 09, Interior - Oct. 09)

December 2008 to July 2009
Demolition of parking garage
Mass excavation and foundations started-July
Structural steel procurement

September 2009
Form and pour foundation
Start structural steel erection

October 2009
Underground site utilities installed
Mass excavation complete
Start mechanical, electrical, plumbing, fire protection installation (rough-in)

December 2009
Structural steel framing to top of podium
Elevated metal decking started
Man hoist available
Start elevator installations

May 2010
Structural steel complete
Precast skin started
Interior wall framing started
Start landscaping

December 2011
Substantial Completion
Dedication Ceremony

First Quarter 2012
Maricopa County – Move in
Final completion

Gilbane / RyanParsons+HDRGouldEvansAECOMArcadis

gilbaneco.com ryancompanies.com