October 2007 to September 2008
Schematic Design
September 2008 to March 2009
Design Development
March 2009 to October 2009
Final Plans-(Core shell Jul. 09, Interior - Oct. 09)
December 2008 to July 2009
Demolition of parking garage
Mass excavation and foundations started-July
Structural steel procurement
September 2009
Form and pour foundation
Start structural steel erection
October 2009
Underground site utilities installed
Mass excavation complete
Start mechanical, electrical, plumbing, fire protection installation (rough-in)
December 2009
Structural steel framing to top of podium
Elevated metal decking started
Man hoist available
Start elevator installations
May 2010
Structural steel complete
Precast skin started
Interior wall framing started
Start landscaping
December 2011
Substantial Completion
Dedication Ceremony
First Quarter 2012
Maricopa County – Move in
Final completion |