Maricopa County
Downtown Court Tower

Have a Question?

Court Tower Project Budget

  Budget Percent of Total Budget Expenditures
(As of Aug 31, 2009)
Percent Expended to Date
Architectural / Engineering $24,592,375 7% $15,724,570 64%
Project Management $8,581,039 3% $3,369,637 39%
Construction $263,682,486 78% $22,073,654 8%
Furnishings, Equip &
Telecom Infrastructure
$23,180,470 7% $186,475 1%
Project Insurance $8,493,967 3% $8,363,594 98%
Contingency $6,010,081 2% $0 0%
Other
(Materials Testing, Environmental, Printing, Plan Review/Permits, Other Misc Costs)
$5,018,582 1% $1,420,877 28%
Total $339,559,000 100% $51,138,808 15%

Court Tower Budget Breakout

Court Tower Budget Expenditures

Gilbane / RyanParsons+HDRGouldEvans AECOMArcadis

gilbaneco.com ryancompanies.com