Downtown Court Tower

Have a Question?

Project Activities

Recent

  • Structural steel erection began in September and is now above ground level
  • The first crane has been placed at the site and is operating
  • Madison Street is now closed from 1st to 3rd Avenues
  • 8” gas line relocation at 2nd Avenue is beginning
  • The first big pour of the Concrete Mat Foundation of more 5-thousand cub yards of concrete is complete
  • S/MBE Workshop for local small businesses was held at the construction sitetrailers, 1 West Jackson Street, on October 1.
  • Most of the work in getting the water pipes and other utility conduits under Jackson Street is complete.
  • The Board of Supervisors approved expenditures of up to $104-million for the next construction segment.

The project is currently on schedule and within the budget.